Autonomous Towers
Sub Contractor · 2021
Our company was engaged by Pilbara Networks to complete detailed earthworks for autonomous towers at Mesa A,J,and H near Pannawonika, ensuring optimal site preparation.
- 01 Remote mobilisation
- 02 Site preparation
- 03 Material transport
- 04 Operational oversight
Remote mobilisation
Transporting tipper trucks and skid steers to the site for efficient earthmoving operations.
Site preparation
Utilising skid steers for grading and leveling the terrain needed for autonomous tower installations.
Material transport
Employing tipper trucks to transport soil and other materials to and from the site for earthworks.
Operational oversight
Ensuring all equipment is operated safely and efficiently, adhering to project timelines and safety regulations.
Challenges
Access limitations
Difficult terrain and narrow access routes restricted the movement of heavy machinery and equipment.
Environmental considerations
Compliance with environmental regulations added complexity to site operations and necessitated additional monitoring.
Exisiting infrastructure
Proximity to existing infrastructure required careful planning and coordination.
Safety hazards
Identifying and mitigating potential safety hazards on-site was a continuous priority to protect workers and equipment.
More projects
Continue through the portfolio — previous and next programmes.

Jandakot stormwater
Engaged by Tracc Civil to install stormwater drainage systems for the Jandakot Industrial Lots project, ensuring effective water management and compliance with local regulations for sustainable development.
View project
Newborough Primary School
We were engaged by Tracc Civil to complete the earthworks, drainage, and car park for Newborough Primary School in Scarborough, ensuring efficient project execution and quality.
View project